ENGS 90: Cost Effective Water Pump for Fond des Blancs, Haiti

In this blog we interviewed Robbie Moss of group 6 who as the title indicates are working on developing a plan for development of a cost effective water pump for Fond des Blanc in Haiti.

Before you go onto the interview, we’ll give you a short description of what ENGS 90 is about. Engs 89-90 are the two project courses at Thayer which every students who wants to earn the B.E degree is required to carry out. The two courses refer to the same project which is spread over two successive terms. These projects are typically sponsored by external agencies including private firms and NGOs which face challenging engineering problems. Student teams select a set of projects and they are allocated a project based on their preference. Project sponsors are vetted and selected by a team of faculty. At the end of the project the student team is required to present its work to a faculty review panel and based upon the strength of their work, students are graded.

Here’s the interview:

Group 6 members: Kevin Dahms; Annie Saunders; Robbie Cholnoky; Robbie Moss

1)Could you tell us about the objective of your project?

Our objective is to improve reliability and cost effectiveness of the water pumping system in the community at Fond des Blancs, Haiti.

2) Could you tell us a little about Fond des Blancs as well?

Well it’s a small village with close to 7000 people. Its very isolated, so it presents a lot of challenges for the working of the present system. Primary amongst it is that it takes a lot of money to transport diesel fuel for the motor at the village.

3) Describe the water pumping system in place now

The existing pumping system consists of a reservoir fed by a stream; water from the reservoir is pumped into a storage tank  by the diesel motor from where the water is gravity fed to the households using PVC pipes. Drawback of using PVC pipes is that since it rains a lot in Haiti, there is runoff and the underground pipes become exposed and liable to breakage. We are working on solving this problem as well.

4.) So what are the primary challenges that you intend to tackle?

The existing water system installed breaks down frequently thus incurring high repair costs, also it works on diesel thus driving up the cost of operation. Our goal is to make the motor run on renewable energy thereby reducing costs and improving the efficiency.

5.) Could you describe how you intend to meet your objective?

We intend to replace the diesel motor for pumping with an electric motor which can be then powered by a renewable source. The options which look the most promising are solar and hydro power. The other options are biomass and wind which are not viable since cost effectiveness for biomass is limited and there is no wind at the location. Further, since the stream head available for damming on the stream is narrow, constructing a dam is difficult. Hence hydro power, though a plausible option is a secondary option we are considering.

6.) What are the challenges in implementing the solar power option for the electric motor?

The challenge with the solar option is that we want to avoid using batteries to keep the system simple. At the same time not using batteries would force us to use a 10Hp motor for pumping water into the tank within a day assuming we get 8 hours of sun every day. Here the motor rating is high for this particular application. And we want to keep the motor power rating low, so if we use a 3Hp motor which is more doable we’ll have to pump for 20 hours in a day, during nights as well thus necessitating the use of batteries. Usage of batteries makes the system more complex because in case of a battery breakdown there’s no immediate technical help owing to the remote location of the community.

So figuring out how best to deal with the trade-off between one of the two system approaches is the major challenge we face.

7.) Could you comment on the progress of the project?

It’s making good progress and we are still working on it but things are liable to change as of now.

8.) Please describe your involvement with the machine shop for your project and about your project sponsor.

We have limited involvement at the machine shop given that our project is more of an engineering consulting project and our project scope is limited to finding an optimal solution for implementation, so we won’t be implementing the solution here.

Our project sponsor is an NGO working in Haiti.

Thank you and we wish your team good luck with your project.

That was the interview with Robbie Moss about his team’s ENGS 390 project. We hope you enjoyed reading it. Also Robbie had mentioned that he’d be sending us his team’s group photo- we are still waiting, but once he shares it it’ll be here.

 

And here it is: in the white t-shirt is Robbie.

 

-Pavan R. Yerram

 

Posted in Blog

Leave a Reply

Your email address will not be published.

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>